A Study on the Cost Estimate System Development Method for Nuclear Power Plant Construction Projects
- Lee, Sang Hyun (Central Research Institute, Korea Hydro & Nuclear Power Co., LTD)
- 발행 : 2017.10.27
초록
Nuclear power plants in Korea are usually built based on a duplicated model; so the project cost data of the preceding unit can be used as reference when estimating the project cost for the succeeding unit. However, since the contracting method is oriented towards the price, empirical factors such as making top-down estimations using the reverse calculation method based on the completion cost of the preceding unit is dominant. In order to develop a project cost database to resolve such problems, the detailed cost boundary of the project cost data must be categorized by project and by system. This study proposes a method to connect the code of account with the base quantities and the IAEA account, and proposes a database structure for the development of a project cost estimation system. The estimation system developed in the future is expected to utilize the proposed project cost data structure.