Development of Delay Responsibility Determination Model based on the Probabilistic Risk Analysis

  • Cho, Ji Hoon (Civil and Environmental Engineering, Dongguk University) ;
  • Lim, Dong Yui (Civil and Environmental Engineering, Dongguk University) ;
  • Kim, Sang Bum (Civil and Environmental Engineering, Dongguk University)
  • Published : 2015.10.11

Abstract

This research attempts to resolve the construction delay issues of indirect delays by developing the "Delay Responsibility Determination Model" (DRM) based on probabilistic risk analysis. DRM is envisioned to provide a way of quantitatively analyzing impacts of delayed activities while considering both direct and indirect influences. With the successful development of DRM, it would be possible to present relative probabilistic measures to all the related stakeholders in terms of their contributions to schedule delays. Upon the development completion of DRM, "Korean Construction Delay Claim/Dispute Resolution Protocols" will also be prepared to facilitate the effective use of DRM.