Optimizing Construction Alternatives for Repetitive Scheduling
반복공정 최적 공법대안 선정 방법
- Published : 2015.05.28
Abstract
Efficient scheduling and resource management are the key factor to reduce construction project budget (e.g., labor cost, equipment cost, material cost, etc.). Resource-based line of balance (LOB) technique has been used to complement the limitations of time-driven scheduling techniques (e.g., critical-path method). Optimizing construction alternatives contributes cost savings while honoring the project deadline. However, existing LOB scheduling is lack of identifying optimal resource combination. This study presents a method which identifies the optimal construction alternatives, hence achieving resource minimization in a repetitive construction by using genetic algorithm (GA). The method provides efficient planning tool that enhances the usability of the system.