Formwork Productivity Analysis Model for Cost-efficient Equipment Operations

  • Hyunsu Lim (School of Civil, Environmental and Architectural Engineering, Korea University) ;
  • Taehoon Kim (School of Civil, Environmental and Architectural Engineering, Korea University) ;
  • Hunhee Cho (School of Civil, Environmental and Architectural Engineering, Korea University) ;
  • Kyung-In Kang (School of Civil, Environmental and Architectural Engineering, Korea University)
  • Published : 2013.01.09

Abstract

In the tall building construction, the slab formwork largely impacts on construction cost. Because productivity of a slab formwork is influenced by a number of and the efficiency of equipment, using the equipment-based construction method, an appropriate equipment input planning is crucial for the productivity. Meanwhile, the general equipment input planning is conducted by intuition based on experience due to the lack of equipment productivity data. Thus, this study develop a simulation model to analyze table formwork productivity and to propose an optimum equipment input plan that reflects the construction process, based on the full consideration of the economic factors. This study developed a simulation model by using CYCLONE and the data for the model was collected by measuring the duration of each unit activity in the tall building where table forms were applied. It is expected that a simulation model helps users to make better decision on the equipment input planning of slab formwork.

Keywords

Acknowledgement

This research was supported by a grant(code#09 R&D A01) from High-Tech Urban Development Program funded by the Ministry of land, transport and maritime affairs.