The verification of the application of grouting in the bottom protection work of sea dikes in the field
그라우팅을 통한 방조제 바닥보호공 차수공법 현장 적용성 검증
- Lee, So-Yeal (Saemangeum Project Office, KRC) ;
- Choi, Sae-Kyung (Saemangeum Project Office, KRC) ;
- Jeong, Il-Han (Rural Research Institute, KRC)
- Published : 2010.09.09
Abstract
By understanding the construction process of sea dikes and the current state of the thickness and speed of fluid in the bottom layer protection work of final closure gaps, a construction method applicable for the blocking of bottom layer work will be selected. The three construction methods selected will be tested in site through various methods, and the reinforcement of bottom layer protection and impervious effect will be verified. The verification results are as follows: 1) The overall riprap layer were 0.5~1.0m thicker than planned so that the grouting depth and grout input amount increased 2) The applied construction methods permeability of riprap layers were improved from