기후요소를 활용한 철골공사기간 예측 시스템에 관한 연구 - 실시간 진도관리 시스템 적용을 중심으로 -

  • 박정로 (한양대학교 건축환경공학과) ;
  • 유승규 (한양대학교 건축환경공학과) ;
  • 김경환 (건국대학교 건축공학과) ;
  • 김재준 (한양대학교 건축환경공학과)
  • Published : 2009.11.14

Abstract

Weather factors affect cost increases and progress management under construction. Because progress schedule is delayed by weather factors, the construction costs are increased. It is an essential element to control the progress schedule applying weather factors to the progress management. This study applies monthly working-day percentages which is estimated by databases of past weather information to RTPM system. Through do progress management in construction projects exactly, will try to minimize risk of process control that do that is to weather factors. Also, will compare calamity in safety supervision side that do that is to weather factors beforehand. Based on the factors and the expected impact of factors together with the weather data during the last 50 years in Seoul region gathered from Korea. Through it, calculated number of month working day of RCA's structural steel work. Studied way that apply to RTPM system.

Keywords