International conference on construction engineering and project management (국제학술발표논문집)
- 2009.05a
- /
- Pages.1334-1339
- /
- 2009
- /
- 2508-9048(eISSN)
A BLOG BASED RISK MANAGEMENT SYSTEM USING SOFT SCHEDULE
- Soo-Myeong Jin (Kyungwon University) ;
- You-Sang Yoon (Lean Construction Research Center) ;
- Myung-Houn Jang (Cheju National University) ;
- Sang-Wook Suh (Kyungwon University)
- Published : 2009.05.27
Abstract
To achieve the best performance of a project, uncertainties involved in the building construction process need to be identified in the planning phase of the project. Uncertainties seldom create a positive impact on construction project, but they almost cause delay and increase costs. Therefore, risk management plays a significant role in construction to minimize risk occurred due to uncertainties of a project. Although the importance of the risk management has been known to the construction industry, it is not enough to be developed to meet the demands of the industry. It has not been enough for Systems to control schedule risks for managers in the field. Therefore, a tool is necessary to efficiently control risks. The propose of this study is to invent Schedule Risk Control System Module to prepare for risks in preconstruction phase.