Case history in prediction of consolidation settlement and monitoring

준설매립 초연약지반의 압밀침하 거동 및 계측 사례

  • 전제성 (한국수자원공사 수자원연구원) ;
  • 이종욱 (한국수자원공사 수자원연구원) ;
  • 임은상 (한국수자원공사 수자원연구원) ;
  • 김재홍 (한국수자원공사 수자원연구원)
  • Published : 2008.10.10

Abstract

Performance of ground improvement project using prefabricated vertical drains of condition, in which approximately 10m dredged fill overlies original soft foundation layer in the coastal area has been conducted. From field monitoring results, excessive ground settlement compared to predicted settlement in design stage developed during the following one year. In order to predict the final consolidation behavior, recalculation of consolidation settlements and back analysis using observed settlements were conducted. Field monitoring results of surface settlements were evaluated, and then corrected because large shear deformation was occurred by construction events in the early stages of consolidation. To predict the consolidation behavior, material functions and in-situ conditions from laboratory consolidation test were re-analyzed. Using these results, height of additional embankment is estimated to satisfy residual settlement limit and maintain an adequate ground elevation. The recalculated time-settlement curve has been compared to field monitoring results after additional surcharge was applied.

Keywords