Study on the Report Conformance Test of IEC 61850 based IED

IEC 61850기반 IED 대상 리포트 적합성 시험에 관한 연구

  • Lee, N.H. (Korea Electric Power Corporation) ;
  • Jang, B.T. (Korea Electric Power Corporation) ;
  • Kim, J.H. (Korea Electric Power Corporation) ;
  • Song, I.J. (Korea Electric Power Corporation) ;
  • An, Y.H. (Korea Electric Power Corporation)
  • 이남호 (한국전력공사 전력연구원) ;
  • 장병태 (한국전력공사 전력연구원) ;
  • 김지희 (한국전력공사 전력연구원) ;
  • 송인준 (한국전력공사 전력연구원) ;
  • 안용호 (한국전력공사 전력연구원)
  • Published : 2008.07.16

Abstract

Korea Electric Power Research Institute has being carried out an IEC 61580 communication service test on IED trial products developed related to power IT project, "The verification of Performance of the Substation Automation System and Its Field Test". This paper presents reporting services of IEC 61850-8-1 and related UCA Test procedures, reporting test items are widely divided into unbuffered report and buffered report and this paper is dealing with unbuffered report.

Keywords