가상건설기반의 건설공사 일정 및 3D객체 연동시스템의 개선된 구축방안
Improved Link System of Schedule and 3D Object for VR-base Construction Project
- 발행 : 2007.04.12
초록
Virtual reality (VR) technology for construction project includes 3D CAD application and 4D CAD system for visualizing construction schedule data. 3D CAD application is more important in the design phase and 4D CAD system is effective tool in the construction phase. This study suggests a methodology to develop VR functions that can be used for project life cycle. The results of this study includes composition algorithms to make VR systems such as bird's eye view system, VR drawings system, VR telepresence system and VR risk management system. Those methodologies can be used for integrated VR system with nD CAD object.