Application to Breakwater Foundation by DCM

DCM 공법에 의한 방파제 기초 적용사례

  • Published : 2006.03.24

Abstract

The DCM(Deep Cement Mixing) Method was introduced domestically in 1985 and has been applied widely to improve stability, increase bearing capacity and reduce settlement of the structure. It has been only performed by the combined equipment to improve the soft ground in coastal areas. But it has qualify-control problems such as interference of waves and improving depth, etc. Therefore DCM Barge of specialist equipment, named by Dong Ji Ho, was equipped with three mixing shafts with four rod and installed GPS system In itself, had been developed in 2005 for the purpose of solving the above problems. This paper represents about Dong Ji Ho's qualify-control system as well as it's first domestic application to in-situ trial test and the original design of the Ulsan breakwater site.

Keywords