FORECASTING THE COST AND DURATION OF SCHOOL RECONSTRUCTION PROJECTS USING REGRESSION ANALYSIS

  • Wei Tong Chen (Dept. of Constr. Engrg, Nat'l Yunlin University of Sci. and Tech.) ;
  • Ying-Hua Huang (Dept. of Constr. Engrg., Nat' Yunlin University of Sci. and Tech.) ;
  • Shen-Li Liao (Graduate School of Engrg. Sci. & Tech., Nat'l Yunlin University of Sci. and Tech.)
  • Published : 2005.10.16

Abstract

This paper collected 132 schools reconstruction projects in central Taiwan, which received the most serious damage from the Chi-Chi Earthquake. Regression analysis was implemented to build the prediction model of the cost and the duration for the collected projects. It is found that the cubic regression models are capable for predicting the cost and the duration of the projects contracted by the central agency of which the contracting awarding approach was based on the most advantageous tendering (MAT) approach. On the other hand, power regression models are capable for predicting the cost and the duration of the projects contracted through the low bid tendering (LBT) approach. It is also found that the performance of the regression prediction model differs in accordance with organizations that contracted the reconstruction projects.

Keywords