SEOUL TOLL PLAZA VALUE ENGINEERING STUDY CONSIDERING PERFORMANCE MEASUREMENT AND LIFE-CYCLE COSTS

  • 발행 : 2005.10.16

초록

Recent increases in construction costs on Korean public works projects, largely due to change orders caused by poorly elaborated design, become a motivation of applying VE process in Korean construction industry. The Seoul Toll Plaza project, recently value analyzed by four VE teams, demonstrates how value management helps save time, money and increase functional performance. The objective of this project is to upgrade and expand existing pay and ticket booths system on "Kyungboo Express Highway", the main artery for the Korean peninsula linking Seoul to Pusan. The value management study generated several innovate alternatives capable of saving up to 50% of project cost from the baseline project plan.