Evaluation on the Dismantling Activities of the KRR-2 Radioisotope Production Facilities

연구로 2호기 동위원소생산시설 해체활동 평가

  • Published : 2003.11.01

Abstract

In accordance with the KRR-1 & 2 decommissioning project, the decontamination and dismantling activities of the KRR-2 auxiliary facilities, radioisotope production facilities, were completed from Aug 2001 to Dec 2002. The auxiliary facilities were composed of the concrete hot-cell, lead hot-cells and several laboratories for the radioisotope production. The dismantling objects are home hoods, experimental desks, sinks, and contaminated inner facilities. For the purpose of the safe decommissioning activity, the method statements and working procedures were set up. The manpower of the total 20,933 man-hour was required and several dismantling equipments were also. The maximum surface contamination is: 9.24 Bq/$\textrm{cm}^2$ in removable contamination and 350,000 cpm in fixed contamination. The total amount of 62.146 Ton was raised as dismantled waste with kinds of the concretes, wood, steels, etc. The collective dose was evaluated as 0.33 mam-mSv during this period.

연구로 1,2호기 해체 사업이 본격적으로 착수하게 됨에 따라 2001년 8월부터 2002년 12월까지 연구로 2호기 부속시설인 동위원소 생산시설을 제염 및 해체하였다. 이 시설은 동위원소 생산용 콘크리트 핫셀, 납 핫셀 및 실험실로 구성되어 있다. 제염ㆍ해체의 대상물은 흄후드, 실험대, 씽크 및 오염된 내부 시설물이다. 안전한 해체 활동을 위해서 각종 지침서 및 절차서가 수립되었다. 해체 활동을 위해 총 20,933 man-hour의 인력이 소요되었고, 드릴링 머신 등 여러 장비가 투입되었다. 실험실에서의 최대 오염도는 유리성 오염도가 $\beta$ : 9.24 Bq/$\textrm{cm}^2$이였고, 고착성 오염도는 350,000 cpm이였다. 해체폐기물은 콘크리트류, 목재류 및 철재류 등으로 총 62.146 Ton이고, 작업자들의 피폭량은 0.33 mam-mSv로 나타났다.

Keywords