Field Measurements with the Construction of Cut and Cover Tunnel

복개 터널구조물의 현장 시공에 따른 계측 분석 사례

  • 박시현 (한국건설기술연구원 토목연구부) ;
  • 이석원 (한국건설기술연구원 토목연구부) ;
  • 이규필 (한국건설기술연구원 토목연구부) ;
  • 배규진 (한국건설기술연구원 토목연구부) ;
  • 전오성 (대림산업주식회사 기술연구소) ;
  • 이종성 (대림산업주식회사 기술연구소)
  • Published : 2002.03.01

Abstract

Field measurements were carried out in this study to investigate the behavior of cut and cover tunnel such as the distribution and the magnitude of the earth pressure during back fill process of the ground material. Three kinds of measuring instruments, such as the earth pressure load cell, the concrete strain gauge and the reinforcing bar meter of embedded type in concrete structure were installed and measured. Earth pressure load cells, installed after construction of the tunnel lining, measure the outside forces acting on the tunnel lining with radial directions. Three load cells were installed at the crown, the right and the left shoulder of the tunnel, respectively. Three sets of reinforcing bar meter were installed in the double reinforcements of the tunnel lining and their locations were the same with the position of the earth pressure load cells. Concrete strain gauge was installed only one site of the upper compressive part at the tunnel crown. Based on the measuring results in the field, the deformation and the earth pressure acting on the tunnel lining were investigated with the back fill process of the ground material. Considerations on the validity of the measuring results were paid. For the analysis of measurements, after dividing back fill process into three steps, various factors which affect on the behavior of tunnel lining were investigated at each step.

Keywords