Development of a system for Project Quality Plan in Connection with Schedule D/B

공정D/B 연계를 통한 품질계획서 운영시스템 개발

  • Published : 2001.11.01

Abstract

Because of preferential treatment in PQ judgement, many construction company got the certification of ISO 9000. But the main objective of them was just certification itself. The ISO 9000 certification which was composed of 20 requirements was a standard just for the manufacturing industry, so it was difficult that it was applied to a business of construction industry. In these reasons, they have revised ISO 9000:l994 which was composed or 20 requirements to ISO 9000:2000 which requests to focus on business process. In this research, we'll develop a System for Project Quality Plan that is related with information of site process in an apartment housing project. This system is intended to increase use of project quality plan in construction sites based on the construction process.

PQ 심사시 가산점 제도에 의해 수많은 건설회사들이 ISO 9000 인중을 획득하였지만, 품질경영시스템의 적극적 활용보다는 인증 자체가 목적이 되는 부작용을 야기 시켰다. 또한 20가지 요구사항 중심의 ISO인증은 제조업 중심의 규격으로, 건설업과 같은 서비스 업종에는 적용하기가 어려웠다. 이러한 이유로 20가지 요구사항 중심의 ISO 9000:1994에서 프로세스 중심의 ISO 9000:2000으로 개정하게 되었고, 이에 따라 새로는 품질경영시스템의 마련이 요구되고 있다 따라서 본 연구에서는 공동주택사업을 중심으로 현장 공정 정보와 연계하여 운영되는 품질계획서 운영시스템을 개발하고, 이를 통하여 현장별로 수행되는 공정을 중심으로 품질관리가 가능하도록 하여 개정된 ISO 9000:2000 규격의 핵심요구사항 중 하나인 프로세스 중심의 접근을 만족시키고자 한다.

Keywords