만경수역 해수 유통시 조석환경변화 고찰

Tidal behavior changes in Mangyeong reservoir area with permitting sea-water intrusion through the sluice gate

  • 발행 : 2001.10.12

초록

As one of the phil-environmental alternative plan of Saemankeum project, gradual development is recommended. The procedure of the Saemankeum project start with the completion of 32 km long sea-dikes which contains two discharge gates until the year 2004. Second step is pre-development of Mangyoung area permitting temporary intrusion of sea water, i.e. tides, by the opening of discharge gate until the environmental evaluation on the water quality of this area secures permanent meet to government's water quality standard. Therefore this study is to predict the future condition of this tidal flat with the point of view tidal environments, salt, water quality, soil mechanics, etc. of Mangyoung area when the sea water still passed in the inland reservoir through the discharge gate.

키워드