Scheduling with regard to start lag in process group

공정 그룹별 Start lag을 고려한 스케쥴링

  • 전태준 (전남대학교 산업공학과) ;
  • 박성호 (전남대학교 산업공학과)
  • Published : 1996.10.01

Abstract

The purpose of this study is developing scheduling logic and program for machining scheduling of automobile part production line with unbalanced processing time. Three rules are developed to minimize slack and effect on other job. Fourth rule is suggested which considered weighted sum of three factors. schedule is generated totally 1, 000 times and then optimal weight parameter is selected. The program is developed to schedule situation to compare with the performance measure, total finish time of machine and total tardiness of part. As a result, the rule which considered weighted sum of three factors is effective for both measure.