Evaluation of Load Rejection to House Load Test at 100% Power for YGN 4
- Sohn, Jong-Joo (Korea Atomic Energy Research Institute) ;
- Jeong, Won-Sang (Korea Atomic Energy Research Institute) ;
- Chi, Sung-Goo (Korea Atomic Energy Research Institute) ;
- Seo, Jong-Tae (Korea Atomic Energy Research Institute) ;
- Kim, Si-Hwan (Korea Atomic Energy Research Institute)
- Published : 1995.05.01
Abstract
The Load Rejection to House Load test at 100% power was successfully performed during the YGN 4 PAT period. In this test, all plant control systems automatically controlled the plant from 100% power to house load operation mode. The LTC code, which was used in the performance analysis during the design process of YGN 3&4, predictions of the test agreed with the measured data demonstrating the validity of the code as well as the completeness of the plant design.