Abstract

This paper presents the shield TBM technology in soft ground tunnelling. In order to perform this study, a scale model test was carried out using the developed small scaled shield TBM machine. The various instrumentations were conducted during the simulation of tunnelling. In addition, the ground behavior due to the shield TBM operation parameters was measured during the simulation. Based on the simulation results, the stability of the ground was evaluated and the fundamental shield TBM tunnelling technique in the soft ground was suggested. In conclusion, design's reliability through laboratory small scale model test about Shield-TBM section was obtained, and both the improvement plan for safety during construction and the construction plan for securing airport runway's safety during tunnel passing by Shield-TBM propulsion were suggested.

References

  1. Attewell, P.B. (1977), "Ground movements caused by tunnelling in soil", Proceeding of Conference on Large Ground Movements and Structures, Cardiff, England, pp. 812-948.
  2. Broms, B.B., Bennermark, H. (1967), "Stability of clay in vertical opening, journal of soil mechanics and foundation engineering", ASCE, Vol. 93, No. SM1, pp. 71-94.
  3. Pantet, A. (1991), "Creusement de galeries a faible profondeur a I'aide d'un tunnelier a pression de boue: mesures in situ et etude theonique du champs de deplacements", These de doctorat, INSA, Lyon.
  4. Peck, R.B. (1969), "Deep excavations and tunnelling in soft ground, state of the art report, proceedings of 7th international conference on soil mechanics and foundation engineering", Mexico City, State of the Art Volume, pp. 225-290.
  5. Kim, S.H., Kim, J.T., Jang, I.S. (2012), "A study on technology of shield TBM tunnelling in mixed ground through the model test", KTA 2012 Symposium November 2, 2012 pp. 113-119.
  6. Schmidt, B. (1969), "Settlements and ground movements associated with tunnelling in soil", Ph.D thesis, University of Illinois.

Cited by

  1. Model test on operation efficiency in the screw conveyor of shiled TBM in soft ground vol.16, pp.2, 2014, https://doi.org/10.9711/KTAJ.2014.16.2.203
  2. Development of simulation equipment system on EPB shield TBM hood operation vol.16, pp.2, 2014, https://doi.org/10.9711/KTAJ.2014.16.2.193